Product Selection and Project Preparation

1. What size basins are Basin-Saver kits designed for?

Basin-Saver kits are designed for 2' x 2' square basins or circular basins approximately 3' in diameter.

2. Will one Basin-Saver kit cover a larger basin?

For basins larger than 2' x 2' or approximately 3' in diameter, two kits may be necessary to complete the installation.

3. What if the damaged area extends more than 2 feet down the basin wall?

A second kit will be needed if the repair area exceeds 2 feet on any damaged wall. Always install the lower section first, then overlap the upper fabric 5" to 6" over the lower fabric.

4. Can Basin-Saver be used on larger structures, such as concrete culverts?

Yes. Custom kits can be prepared for larger applications. Contact Basin-Saver by email with the project dimensions (contact@basin-saver.com). Additional pricing will apply based on the project specifications.  

5. Can one person install a Basin-Saver kit?

Yes. Basin-Saver kits are designed for installation by one or two people. However, the X-tra Strength Kit is more user-friendly and easier for a single installer to apply.

6. Which kit is recommended for a single installer?

The Basin-Saver X-tra Strength Kit is recommended because it allows the installer to treat one wall at a time and provides more flexibility during installation.

7. What should I do before starting an installation?

Review the installation video at Basin-Saver.com, gather all necessary tools and safety equipment, assess the work area, and establish a safe work zone using barricades, cones, and/or caution tape.

Moisture and Surface Preparation

8. Can Basin-Saver be installed in a damp basin?

Basin-Saver may not work as intended if the basin is damp, has recently experienced rainfall, or consistently holds water. The basin walls must be sufficiently dry to achieve proper epoxy adhesion. 

9. What moisture level is recommended before installation?

For optimum adhesion, basin walls should have a moisture reading of 5% or less. A reading of 7% or less is considered acceptable for good adhesion.

10. Do I need to use a moisture detector before installation?

Yes. We strongly recommend using a moisture detector to test the basin walls before installation. Do not rely solely on visual inspection to determine whether the walls are dry enough.

11. What should I do if the basin walls are too damp?

Use a fan or small space heater to circulate air inside the basin. Heated air is preferred when available. Once the walls have dried, test the moisture level again before proceeding. Do not place any electrical item in any basin that is retaining water.

12. Do existing cracks and damaged concrete need to be repaired before installation?

Yes. Replace broken or missing blocks, complete tuckpointing, treat cracks with hydraulic cement, and perform all other necessary structural repairs before preparing the walls for Basin-Saver installation.

13. How long should newly poured concrete cure before installing Basin-Saver?

Recently poured concrete walls must cure for at least 28 days before installation. This allows excess moisture to escape. Always verify the moisture level with a moisture detector before proceeding.

14. Why is grinding the basin walls recommended?

Grinding removes approximately 1/8" to 1/4" of concrete, along with dirt, debris, oil, mildew, and other contaminants. It also creates an orange-peel-like surface texture that promotes epoxy adhesion.

15. What tools should be used to prepare the basin walls?

A diamond plate or angle grinder is recommended to remove the surface layer of concrete. A hand brush, small brush, or forced-air blower can then be used to remove remaining dust.  

16. Is grinding the only way to prepare basin walls?

No. An alternative is to apply a skim coat, also known as a slurry coat or slurry seal. However, installations using the skim-coat method are covered by a 2-year Full Money Back Warranty only.

17. Can I pressure wash the basin instead of grinding?

Yes, if the walls are already smooth and free of pores. Use a pressure washer rated at least 2,500 PSI to remove dirt, loose debris, moss, and mildew. Soap may be necessary to remove oil.

Keep in mind that pressure washing adds moisture to the basin and typically requires approximately 24 hours of drying time before installation. Always retest moisture levels before applying epoxy.

Support Pins and Epoxy Preparation

18. Why are support pins required for Basin-Saver installation?

The support pins are essential to the integrity of the Basin-Saver system. They provide additional reinforcement and help account for potential installation errors, oversights, or moisture detector inaccuracies.

19. How many support pin holes should be drilled?

Four holes should be drilled at the designated locations, approximately 6" to 12" below the top of the installation area.

20. What size drill bit should be used for the support pin holes?

Use a 3/8" diameter concrete drill bit long enough to penetrate the entire basin wall, typically 12" to 16".

21. How far must the fiberglass pins extend into the basin?

Each fiberglass pin must extend at least 1" into the basin. This is a critical installation requirement. No warranty is provided if the pins do not extend at least 1" into the basin.

22. Does the angle of the drilled holes matter?

No. The angle does not matter as long as the pin extends at least 1" into the basin after installation. However, pins installed at sharp angles should be monitored to ensure they do not slide into the holes.

23. Should I clean the support pin holes before injecting epoxy?

Yes. Remove as much concrete dust as possible using a high-powered vacuum or forced-air blower. Dust left inside the holes can interfere with proper epoxy bonding.

24. What should I do if a fiberglass pin fits too loosely or too tightly?

Test each hole with an 18" fiberglass pin before injecting epoxy. If necessary, use a hammer to gently tap the pin into place. Make sure the pin can still be removed before applying epoxy.

25. What happens if an 18" fiberglass pin falls completely into a drilled hole?

The Installation Essentials Kit includes six 6" carbon fiber pins that can be used as replacements or additional support. Add extra epoxy into the hole as needed before inserting the shorter pin behind the 18" pin. A hammer may be needed to seat it properly.

26. How quickly does the epoxy begin to cure?

The epoxy begins curing approximately 15 to 20 minutes after application. Installers should work efficiently and have all materials and tools ready before mixing or applying epoxy.

27. Do I need to wear gloves when working with epoxy?

Yes. Always wear rubber gloves when handling and applying epoxy.

Carbon Fiber Fabric Installation

28. How is epoxy applied to the basin walls?

Apply epoxy to each wall using a back-and-forth motion. Use the plastic spreader to distribute the epoxy evenly across the entire application area. Extend the epoxy approximately 1" beyond the marked installation area to accommodate wall variations.

29. How do I prevent air bubbles when installing the carbon fiber fabric?

Smooth the fabric with your hands and the plastic epoxy spreader as it is applied. Work the fabric into the contours of the walls and corners, ensuring there are no trapped air bubbles.

30. Does the carbon fiber fabric need to be saturated with epoxy?

Yes. After positioning the fabric, apply an additional saturating layer of epoxy over the entire surface. Use the plastic spreader to ensure complete coverage and remove any air bubbles.

31. How much should the standard carbon fiber fabric overlap?

The standard kit's carbon fiber fabric should overlap approximately 6" where the beginning and ending sections meet.

32. How is the Basin-Saver Standard Kit fabric installed?

The Standard Kit includes a 10' x 24" carbon fiber fabric roll. Begin at a corner or near a support pin on the first epoxy-coated wall. Keep the fabric horizontally aligned, smooth it into the walls and corners, and continue around all four walls until the fabric overlaps its starting point by approximately 6". Finish by applying a saturating layer of epoxy over the fabric.

33. How is the Basin-Saver X-tra Strength Kit fabric installed?

The X-tra Strength Kit uses individual fabric pieces. First, install one 2' x 2' carbon fiber square on each epoxy-coated wall. There should be no overlap at this stage. Saturate the fabric with epoxy, then install a 1' x 2' fabric piece in each of the four corners, with approximately 6" extending onto each adjoining wall. Finish by saturating all corner pieces with epoxy.

34. Does the fabric need to fit perfectly into every corner?

For the Standard Kit, use the plastic spreader to work the fabric deeply into each corner. With the X-tra Strength Kit, the initial 2' x 2' fabric squares do not need to fit perfectly into every corner because separate corner reinforcement pieces are installed afterward.

35. How should epoxy be spread over the carbon fiber fabric?

A recommended technique is to apply epoxy from the bottom of the basin and spread it upward toward the top. This helps distribute the epoxy over the fabric.

36. What should I do if a support pin is covered by the carbon fiber fabric?

Use a cutting tool to make a small hole in the fabric where the pin is located. Carefully push the pin through the fabric without driving it farther into the wall.

Epoxy Curing and Waterproofing

37. How long does the epoxy need to cure before waterproofing?

Allow the epoxy to cure for at least 24 hours before applying the waterproof membrane.

38. How can I tell if the epoxy has fully cured?

After the minimum 24-hour curing period, gently touch the epoxy with your fingertip. Cured epoxy may still feel tacky, but it should not transfer or stick to your finger. If epoxy transfers to your finger, allow additional curing time.

39. Can I reopen the area to traffic while the epoxy is curing?

The instructions allow installers to either keep barricades in place or replace the drain grate and reopen the area to traffic while the epoxy cures. Follow appropriate job-site safety procedures.

40. When should the waterproof membrane be applied?

Apply the waterproof membrane only after the epoxy has fully cured.

41. How should the waterproof membrane be applied?

Begin by using a small paintbrush to coat the corners of the basin. Then use a paint roller to apply the waterproofing material to each wall. Ensure the entire carbon fiber fabric is covered and no fabric remains visible.

42. How far should the waterproof membrane extend beyond the carbon fiber fabric?

The waterproof membrane should extend at least 2" to 4" above and below the carbon fiber fabric.

43. What happens if the carbon fiber fabric is still visible through the waterproof membrane?

Once the first coat has fully cured, apply a second coat wherever the carbon fiber fabric remains visible.

44. How quickly does the waterproof membrane begin to cure?

Depending on temperature, the waterproofing material may begin curing within 10 to 15 minutes. Once a film develops on the surface, additional material cannot be applied until the initial coat has fully cured.

45. How long should the waterproof membrane cure?

Allow at least 24 hours for the waterproof membrane to cure.

46. When should the Basin-Saver Warranty Badge be installed?

Install the Warranty Badge before the waterproofing material fully cures so the badge becomes part of the membrane.

47. What information needs to be written on the Warranty Badge?

Use a permanent marker to write the installation date clearly and in large enough lettering to be read from a few feet away.

48. Where should the Warranty Badge be placed?

Place the badge on a basin wall where it can be seen through the drain grate. A location a few inches above one of the support pins is generally recommended. Walls exposed to sunlight are preferable for visibility.

Deep Basin Installations and Safety

49. Can Basin-Saver be installed in basins deeper than 4 feet?

Yes, but additional precautions are required. For installations deeper than approximately 4 feet below the drive surface, use the Basin-Saver X-tra Strength Kit and follow the additional deep-basin installation instructions.

50. How many walls can be treated at one time in a deep basin?

Install no more than two adjacent walls at a time. Allow those walls 24 to 48 hours to dry before installing the remaining walls.

51. Why should no more than two adjacent walls be installed at once in a deep basin?

Installing more than two adjacent walls at once creates a risk of the installer becoming stuck against a basin wall as the epoxy cures. Limiting the installation to two adjacent walls helps reduce this serious safety hazard.

52. Is a second person required for deep basin installations?

Yes. Always have a partner stationed on the drive surface above the basin who can assist in an emergency.

53. What ventilation precautions are necessary for deep basin installations?

Provide proper ventilation using a fan, forced-air system, or make-up air system. A ventilation mask rated for concrete dust and epoxy is recommended.

54. What emergency precautions should be taken before entering a deep basin?

Ensure there is a clearly established and easily accessible entry and exit route. A partner must remain above the basin at all times to assist if an emergency occurs.

55. What should an installer do if clothing becomes stuck to curing epoxy?

The installation instructions warn that an installer could become trapped against a wall if too many adjacent walls are treated simultaneously. If clothing becomes stuck, the instructions advise having a knife or scissors immediately available to cut the clothing and escape. If epoxy bonds to skin, serious injury may result. Prevention through proper installation sequencing is essential.

56. What personal protective equipment should be used during installation?

Recommended protective equipment includes:

  • Safety glasses or eye protection.

  • Dust mask or respirator rated for concrete dust and epoxy, as appropriate.

  • Rubber gloves when handling epoxy.

  • Protective clothing.

  • Basin-Saver Belly-Saver foam pad to protect knees and ribs while working inside the basin.

57. What are the primary safety concerns when installing Basin-Saver?

The primary concerns include concrete dust exposure, eye injuries, epoxy exposure, inadequate ventilation, moisture-related adhesion problems, and the risk of becoming trapped inside a deep basin.

58. Is Basin-Saver responsible for injuries resulting from improper installation practices?

The safety notice states that Basin-Saver is not responsible for injuries, damages, or deaths that may occur during installation. Installers must follow all safety instructions and take appropriate precautions.

Installation Time and Warranty

59. How long does a typical Basin-Saver installation take?

Installation time varies depending on basin conditions, preparation requirements, and the kit being used. Individual estimated task times are:

Installation task

Approximate time

Structural wall repairs

30 minutes–2 hours

Grinding / Skim Coating wall surfaces

20–30 minutes

Drilling and installing support pins

10–15 minutes

Applying epoxy to walls

15–20 minutes

Applying Standard Kit fabric

20 minutes

Applying X-tra Strength Kit fabric

30 minutes

Applying waterproof membrane and badge

15–20 minutes

These estimates do not include required drying and curing periods, which can add 24 hours or more to the project.

60. Does pressure washing increase installation time?

Yes. Pressure washing typically adds approximately 24 hours to the project because the water must evaporate before epoxy installation. A fan or small space heater can help reduce drying time.

61. Does the skim-coat installation method affect the warranty?

Yes. Installations using the skim-coat or slurry-coat preparation method have a 2-year Full Money Back Warranty only.

62. Is the support pin requirement connected to the product warranty?

Yes. All support pins must extend at least 1" into the basin. The installation instructions specifically state that no warranty is provided if this requirement is not met.

63. Where can I watch Basin-Saver installation videos?

The primary installation video is available at Basin-Saver.com . Additional installation videos are available on YouTube.  Search "Basin Saver" for YouTube videos.

Miscellaneous Questions

 64. Can Basin-Saver be installed if water regularly collects inside the basin?

Basin-Saver may not perform as intended if the basin consistently holds water or does not drain properly. The underlying moisture problem should be addressed, and the walls must meet the required moisture readings before installation.

65. Can I skip grinding if the basin walls look clean?

Not necessarily. Grinding is recommended because it removes contaminants and creates the surface texture needed for optimum adhesion. Pressure washing is an alternative only when walls are already smooth and free of pores.

66. Can I apply waterproofing material over epoxy that has not fully cured?

No. The epoxy must be fully cured before applying the waterproof membrane. Allow at least 24 hours and verify that epoxy does not transfer to your finger.

67. Can I apply another layer of waterproofing material once the first layer begins developing a film?

No. Once the waterproofing material begins developing a film, additional material cannot be applied. Plan the application so that all necessary areas are covered before this happens.  Or apply a 2nd coat after the initial coat has fully cured.

68. What is the purpose of the Basin-Saver Belly-Saver?

The Belly-Saver is a foam pad designed to protect the installer's knees and ribs while reaching into the basin to prepare and treat the interior walls.

69. What is the most important thing to remember before starting installation?

Proper preparation is essential. Verify moisture levels, complete structural repairs, properly prepare the basin walls, install all required support pins, and ensure all safety precautions are in place before applying epoxy.  *Check for dry weather!

Important Installation Reminders

For quick reference, these are the critical requirements installers should remember:

  • Moisture: 5% or less is optimal; 7% or less is acceptable for good adhesion.

  • Concrete preparation: Remove approximately 1/8" to 1/4" of concrete when grinding.

  • Support pins: All pins must extend at least 1" into the basin.

  • Fabric overlap: Standard Kit fabric should overlap approximately 6".

  • Multiple repair sections: Overlap upper fabric 5" to 6" over lower fabric.

  • Epoxy curing: Allow at least 24 hours before waterproofing.

  • Waterproof membrane: Extend 2" to 4" beyond the fabric.

  • Waterproof membrane curing: Allow at least 24 hours.

  • New concrete: Allow at least 28 days to cure before installation.

  • Deep basins: Use the X-tra Strength Kit, treat no more than two adjacent walls at a time, and always have a partner above the basin.